microsoft-project-training-courses - Viewing resource costs

resolvedResolved · Low Priority · Version Standard

replyReply Wed 4 Apr 2007, 13:55Delegate Caroline said...

Caroline has attended:
Project Intro Intermediate course

Viewing resource costs

I have entered a daily cost for my project resources. How can I get those costs to appear in the 'Cost' column in the gantt view?

For upcoming training course dates see: Pricing & availability

replyReply Thu 12 Apr 2007, 14:36Trainer Andrew said...

RE: Viewing resource costs

Hi Caroline, thanks for your question.

In the Gantt chart view click on a column to choose the point where you would like the cost information to be displayed. From the insert menu choose column and from the dialog box that appears select the cost field.

Wherever you assign a resource that has an associated cost to a task, Project will calculate the cost for that task and display it in appropriate cell of the cost column.

Do let us know if you have any further questions.

Kind regards,

Andrew

 

Ms project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips