Baseline

resolvedResolved · Low Priority · Version 2007

replyReply Tue 1 Mar 2011, 16:15Delegate Ben said...

Ben has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Baseline

How do you add a baseline

For upcoming training course dates see: Pricing & availability

replyReply Tue 1 Mar 2011, 20:27Trainer Rodney said...

RE: Baseline

Hello Ben,

Hope you enjoyed your Microsoft Project Intro Intermediate course with Best STL.

Thank you for your question regarding adding a baseline to a project. Change views to the 'Tracking Gantt' view and then click 'Tools' menu > 'Tracking' > 'Set Baseline'. In the dialogue box accept the defaults if you are setting the baseline for the first time and click OK. This action will create a second set of bars under the current bars with the same start and finish dates.

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

 

Please browse our web site to find out more about
2002 microsoft project training and other Microsoft training courses.

Ms project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.