Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft+project+training - Resource Report Customisation
microsoft+project+training - Resource Report Customisation
Resolved · Low Priority · Version Standard
Bronwyn has attended:
Project Advanced course
Resource Report Customisation
How do I customise the resource usage report to include the project name / summary tasks for each task. At the moment I can not see which project a resource's task relates to.
For upcoming training course dates see: Pricing & availability
RE: Resource Report Customisation
Hi Bronwyn
Unfortunately crosstab reports such as this one can't be modified to add further columns to the display. However you might want to approach this in a different way and rather than create or modify a report simply modify the resource usage view (View > More views > resource usage) And add the fields you wish to display (e.g. project and name) and from file > page setup prepare the view for printing.
Hope this helps Bronwyn - do let us know if you have further questions.
Kind regards,