Setting a start date for a new project using a template

resolvedResolved · Low Priority · Version 2007

replyReply Thu 30 Jun 2011, 09:32Delegate Shamim said...

Shamim has attended:
Project Intermediate course

Setting a start date for a new project using a template

Hello
Can you please remind me how to set a start date for a new project using an already assembled template?
Thanks
Shamim

For upcoming training course dates see: Pricing & availability

replyReply Thu 30 Jun 2011, 10:21Trainer Andrew said...

RE: Setting a start date for a new project using a template

Hi Shamim

Thank you for your question. You can access the Adjust Dates button by turning on the Analysis toolbar. Go to View > Toolbars > Analysis

When you click Adjust dates and enter a new date MS Project will move the project to the date you set, it will also re-calculate any constraints in the plan so that slack (float) is also preserved.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

replyReply Thu 30 Jun 2011, 10:22Delegate Shamim said...

RE: Setting a start date for a new project using a template

Gosh; that was quick! Many thanks Andrew; much appreciated.
Shamim

replyReply Thu 30 Jun 2011, 12:21Trainer Andrew said...

RE: Setting a start date for a new project using a template

Hi Shamim

You're very welcome. All the best with your project.

Kind regards,
Andrew

Thu 7 Jul 2011: Automatically marked as resolved.

 

Please browse our web site to find out more about
server course london and other Microsoft training courses.

Ms project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard