Forum home » Delegate support and help forum » Microsoft Project Training and help » Critical path

Critical path

resolvedResolved · Medium Priority · Version 2010

replyReply Thu 7 Jul 2011, 15:59Delegate David said...

David has attended:
Project Introduction course

Critical path

How can I show critical tasks?

For upcoming training course dates see: Pricing & availability

replyReply Fri 8 Jul 2011, 10:28Trainer Rodney said...

RE: Critical path

Hello David,

Hope you enjoyed your Microsoft Project Introduction course with Best STL.

Thank you for your question regarding critical tasks.

Firstly, I'd like to answer your question with a little background. Whenever you begin entering tasks in Auto Scheduled mode the resulting current bars in the Gantt chart are a blue colour. To view all the critical tasks you must select the Format ribbon in the Gantt Chart Tools contextual tab, then from the Bar Styles group, click the Critical Tasks check box. The current bars in the Gantt Chart which are critical will now be a red colour. If there are any bars still blue, it is because they have some slack time.

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Thu 14 Jul 2011: Automatically marked as resolved.

 

Please browse our web site to find out more about
+project server +training and other Microsoft training courses.

Ms project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard