Forum home » Delegate support and help forum » Microsoft Project Training and help » Resources
Resources
Resolved · Low Priority · Version 2007
Kisha has attended:
Project Intermediate course
Excel Intermediate course
Resources
HOw do I reallocate resources
For upcoming training course dates see: Pricing & availability
RE: resources
Hi Kisha
Thank you for your question. One way to change a resource on a task is to double click the task in question. From the Resources tab find the name of the resource and click on it. From the dropdown list that appears choose the name of the person you wish to swap for the resource.
I hope this helps - do let me know if you have any further questions.
Kind regards,
Andrew
Tue 19 Jul 2011: Automatically marked as resolved.
|
