Progress line

resolvedResolved · Low Priority · Version 2010

replyReply Fri 8 Jul 2011, 16:15Delegate Agnieszka said...

Agnieszka has attended:
Project Intro Intermediate course

Progress line

How I can update progress bar?

For upcoming training course dates see: Pricing & availability

replyReply Tue 12 Jul 2011, 15:19Trainer Andrew said...

RE: Progress line

Hi Agnieszka

Thank you for your question. There are a number of ways of progressing your tasks.

A quick way is to double click the name of the task and then on the general tab to key in the % complete you would like to record.

While this is quick a more accurate result can be achieved by clicking on the Task Ribbon, the clicking on the dropdown beside the "Mark on Track" button and choosing Update Tasks.

In the dialogue box that appears you can set useful values such as actual as well as entering real start and finish dates.

I hope this helps - do let me know if you have any further questions.

Kind regards,
Andrew

Tue 19 Jul 2011: Automatically marked as resolved.

 

Please browse our web site to find out more about
project server training and other Microsoft training courses.

Ms project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard