How I can update progress bar?
For upcoming training course dates see: Pricing & availability
RE: Progress line
Hi Agnieszka
Thank you for your question. There are a number of ways of progressing your tasks.
A quick way is to double click the name of the task and then on the general tab to key in the % complete you would like to record.
While this is quick a more accurate result can be achieved by clicking on the Task Ribbon, the clicking on the dropdown beside the "Mark on Track" button and choosing Update Tasks.
In the dialogue box that appears you can set useful values such as actual as well as entering real start and finish dates.