Schedule Adjustments

resolvedResolved · High Priority · Version 2007

replyReply Tue 19 Jul 2011, 15:16Delegate Cheren said...

Cheren has attended:
Project Advanced course

Schedule Adjustments

I am entering %complete using the Update Task tool. I'm entering actual and remaining duration.
However the resultant date that is then calculated is wrong.

E.g task of 20 days that was due to start on 06/07 and finish on 02/08. It actually started on 08/07, and is as of the status date at 15/07 only 5% complete. I have entered actual start 08/07, 1 actual duration and 19 remaining. This should push the date out to 11/08 (19 days from status date 15/07, but MSP calculates this as 31/08.

It miscalculates on a number of tasks where progress is either ahead or behinf schedule or has not moved since the last status date. However on some other tasks, it calculates perfectly correctly!

Please help!

For upcoming training course dates see: Pricing & availability

replyReply Wed 27 Jul 2011, 09:18Trainer Simon said...

RE: Schedule Adjustments

Hi Cheren,

Thank you for your enquiry.

Is it possible to send a copy of the project with an exact description of what you are trying to achieve and the tasks that are causing problems.

Please send it to sk.

Regards

Simon

Tue 2 Aug 2011: Automatically marked as resolved.

 

Please browse our web site to find out more about
microsoft project server training london and other Microsoft training courses.

Ms project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.