Multiple projects within one overall programme

resolvedResolved · Low Priority · Version 2007

replyReply Wed 5 Oct 2011, 17:54Delegate David said...

David has attended:
Word Advanced course
Finance for Non-Financial Managers course

Multiple projects within one overall programme

Can a multiple programme be deveolped into one overall schedule with the same and/or different resource allocations?

For upcoming training course dates see: Pricing & availability

replyReply Mon 10 Oct 2011, 16:55Trainer Andrew said...

RE: Multiple projects within one overall programme

Hi David

It is possible to share the same team of resources across multiple projects. Let me know if this would help. To set this up you will need to create a Resource pool which is a central pool containing the resources that will be shared across the projects. To create this make a new Project file, go straight to the resource sheet and add your resources. The Resource Pool is not used for recording tasks. Save the Resource Pool and keep it open.

Next open one of the project files that needs to connect to the pool in order to use the shared resources. On the Resource ribbon click Resource Pool > Share Resources and from the dialog box choose to use resources from the resource pool file (which you left open in the background) and click on OK.

Now you will be able assign resources from the central pool.

Repeat this process with the remaining plans that should share the resources in the pool. If the plans you add already have resources then they will be added to the entries in the Resource Pool.

Save and close all files.

Once a project has been connected to the resource pool however it will only be possible to add new resources and share them from the pool.

The next time you open the resource pool you will be offered three options. The last option opens the resource pool in read / write mode and also creates a merged file with all the sharer files already inserted. This combined plan shows the all the projects using resources from the pool.

I hope this is helpful - if you have any questions please do let me know.

Kind regards,
Andrew

Mon 17 Oct 2011: Automatically marked as resolved.

 

Please browse our web site to find out more about
microsft office project 2003 courses in london and other Microsoft training courses.

Ms project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard