MS Project 2010

resolvedResolved · Low Priority · Version 2010

replyReply Wed 30 Nov 2011, 17:01Delegate Rachael said...

Rachael has attended:
Project Intro Intermediate course

MS Project 2010

How do I create a report to show any resource constraints against time?

For upcoming training course dates see: Pricing & availability

replyReply Fri 2 Dec 2011, 16:32Trainer Andrew said...

RE: MS Project 2010

Hi Rachel

Thank you for your question. Project has a built in report that might provide the information you are looking for.

Take a look at the Project Ribbon then choose reports. From the dialogue box that opens choose Workload and then Resource Usage.

This reports shows tasks, assigned resources and the amount of allocated work assigned to them.


You can also view this information in the project plan itself by switching to the resource usage view.

I hope this helps - do let me know if you have any further questions.

Kind regards,
Andrew

 

Please browse our web site to find out more about
microsoft project server testimonials and other Microsoft training courses.

Ms project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard