RE: Project.
Hi Amina
Thank you for your question. You can move a project using the Move button which is on the Project ribbon. When you use this button a dialogue box will open and allow you specify a new date. The project is moved to the date and any constraints in your plan are adjusted so any Slack is preserved.
I hope this helps - do let me know if you have any further questions.
Kind regards,
Andrew