Hyperlinks against tasks / project

resolvedResolved · Medium Priority · Version 2010

replyReply Fri 2 Dec 2011, 10:58Delegate Rachael said...

Rachael has attended:
Project Intro Intermediate course

Hyperlinks against tasks / project

Hello, Can I add a hyperlink from a task to another document / website?

Or a hyperlink for the project somewhere - i.e. to the business case saved in an seperate word document?

Thanks

Rachael

For upcoming training course dates see: Pricing & availability

replyReply Sun 4 Dec 2011, 13:39Trainer Rodney said...

RE: Hyperlinks against tasks / project

Hello Rachael,

Hope you enjoyed your Microsoft Project Intro Intermediate course with Best STL.

Thank you for your question regarding working with hyperlinks.

First decide which task you would like to place the hyperlink to. Select the task, then right-click and choose the Hyperlink option at the bottom of the menu list. From the Insert Hyperlink dialogue box select whichever option you require on the left hand side. If you wish to link to a web site simply enter the full address into the address box near the bottom of the dialogue box. Then click OK.

To link to a another application such as a Word document, you need to browse to the file, then after selecting the file click the OK button to complete the action.

You will find that Project has now placed a Hyperlink icon into the Indicators column. Simply click the icon, accept the message that appears and then the file will automatically be opened.

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

 

Please browse our web site to find out more about
courses microsoft project london and other Microsoft training courses.

Ms project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.