Resources, teams and names

resolvedResolved · Low Priority · Version 2010

replyReply Fri 6 Jan 2012, 10:16Delegate Benjamin said...

Benjamin has attended:
Project Advanced course

Resources, teams and names

Good morning!

On our course we spoke about project resources and how to attach them to tasks. We used generic notation, like job titles (e.g. welder, electrician) to name them, which is great, because it is clear what type of person is needed on the project schedule.

I was just wondering if Project has a means of understanding who (e.g. Joe Bloggs, John Doe) held each of those jobs, so you could later allocate actual people to roles after the execution of the project begins? Or is that sort of thing too low-level to concern Project?

Many thanks in advance of any insights

Ben

For upcoming training course dates see: Pricing & availability

replyReply Mon 9 Jan 2012, 16:41Trainer Rodney said...

RE: Resources, teams and names

Hello Ben,

Thank you for your question regarding naming resources.

There is no right or wrong way to do this. Some project managers prefer to use names whilst others use titles... the choice is yours. There is a way to include both name and title into the resource sheet. You can use the initials column by changing the width and editing the title. You can also insert a new text column and use this to add names. Just edit the title.


I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

replyReply Wed 18 Jan 2012, 10:54Delegate Benjamin said...

RE: Resources, teams and names

Thank you, Rodney

Mon 16 Jan 2012: Automatically marked as resolved.

 

Please browse our web site to find out more about
ms project 2010 london course and other Microsoft training courses.

Ms project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips