Resource overallocation issue with MS Project 2010

resolvedResolved · Medium Priority · Version 2010

replyReply Fri 3 Feb 2012, 10:53Delegate Benedict said...

Benedict has attended:
Project Intro Intermediate course

Resource overallocation issue with MS Project 2010

I am working in a project where I have to allocate several resources to various tasks and each time I assign a resource to a task I get a warning indicator that the resources are over allocated. These resources have been previously allocated to other tasks within the project and as they will be working on multiple tasks at different times and some times at the same time, is there a way I could schedule the resources so as to avoid the overallocation issue?

For upcoming training course dates see: Pricing & availability

replyReply Tue 7 Feb 2012, 10:31Trainer Rodney said...

RE: Resource overallocation issue with MS Project 2010

Hello Benedict,

Thank you for your question regarding resource allocation issues.

Determining the amount of time a resource works on a number of different tasks, some of which are concurrent, can be a bit tricky. However, once you have worked this out all you have to do when assigning a resource to a task is click in the units column and enter the percentage figure (the amount of time a resource is expected to work on that particular task) and press enter to assign.

So, by entering a percentage of time into the units column for each task, you are scheduling a resource's effort to be spent on a particular task. If tasks run concurrently the total percentages for one resource should not exceed 100% or else you will still get the 'Red Man'.

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

Mon 13 Feb 2012: Automatically marked as resolved.

 

Please browse our web site to find out more about
project+server+courses and other Microsoft training courses.

Ms project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard