microsft+office+project+2003+courses+in+london - milestones
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsft+office+project+2003+courses+in+london - Milestones

microsft+office+project+2003+courses+in+london - Milestones

resolvedResolved · Low Priority · Version Standard

replyReply Fri 20 Apr 2007, 16:21Delegate David said...

David has attended:
Project Intro Intermediate course

Milestones

Why do my milestones all move to the same end date, despite having links to earlier tasks?

For upcoming training course dates see: Pricing & availability

replyReply Fri 20 Apr 2007, 16:47Trainer David said...

RE: Milestones

David

as discussed after you had posted your question, you had scheduled from the end dates and did not have a link from the milestone to another task then project puts it in the only place it knows, at the end date.

hope this ansewrs your question

regards

david


 

Ms project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips