ms+project+2003+training - Holidays/non-working days

resolvedResolved · Low Priority · Version Standard

replyReply Thu 26 Apr 2007, 13:37Delegate Sarah said...

Sarah has attended:
Project Intro Intermediate course

Holidays/non-working days

How can I view non-working days on the gantt chart?

For upcoming training course dates see: Pricing & availability

replyReply Thu 26 Apr 2007, 15:46Trainer David said...

RE: Holidays/non-working days

Sarah

all non working time is shown as default by grey bands going vertically down the page, unless the format as been changed.

I hope this answers your question

regards

david howarth

 

Ms project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes