microsoft project training london - Baseline

resolvedResolved · Low Priority · Version Standard

replyReply Fri 4 May 2007, 16:40Delegate Antony said...

Antony has attended:
Project Intermediate course
Project Introduction course

Baseline

how do you create a baseline

For upcoming training course dates see: Pricing & availability

replyReply Wed 16 May 2007, 15:50Trainer Andrew said...

RE: baseline

Hi Antony

Thanks for your question. Creating a baseline is very straightforward. Just go to the tools menu, choose tracking then Save Baseline.

Hope this was helpful - do let us know if you have any further questions.

Kind regards,

Andrew

 

Ms project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard