microsoft project courses london - Constraint Times

resolvedResolved · Low Priority · Version Standard

replyReply Thu 10 May 2007, 14:10Delegate Natasha said...

Natasha has attended:
Project Intro Intermediate course

Constraint Times

If I had an event date already decided, how could i put this in the gantt chart without making many contstraints?

For upcoming training course dates see: Pricing & availability

replyReply Thu 10 May 2007, 16:57Trainer Andrew said...

RE: Constraint Times

Hi Natasha

Thanks for your question. Your task will need a constraint of some kind if you are working to a specific date. Project would prefer your constraints to be partial (such as start no earlier than) rather than full (must...)

The remaining tasks can be left with no constraint so that Project is able to calculate your dates for you.

I hope this helps - do let us know if you have any other questions.

Kind regards,

Andrew

 

Ms project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard