microsoft project course - Milestones

resolvedResolved · Low Priority · Version Standard

For upcoming training course dates see: Pricing & availability

replyReply Tue 5 Jun 2007, 13:05Trainer Andrew said...

RE: milestones

Hi There are at least five ways of doing this. Three of the most common ways however are:

left click (and drag) from one bar in the Gantt chart to another
block select two or more tasks and click on the link tasks button on the toolbar
double click a task and from the predecessors tab choose a task

Hope this helps - do let us know if you have any further questions.
Thanks

Andrew

 

Ms project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips