Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft project course - Milestones
microsoft project course - Milestones
Resolved · Low Priority · Version Standard
trainer has attended:
Dreamweaver 8 Introduction course
Dreamweaver 8 Intermediate course
Powerpoint Intermediate Advanced course
Project Intro Intermediate course
Access Intermediate course
Project Advanced course
Dreamweaver 8 Introduction course
Excel VBA Intro Intermediate course
Excel VBA Intro Intermediate course
Excel VBA Intro Intermediate course
Dreamweaver 8 Introduction course
Project Intro Intermediate course
Project Introduction course
Project Intro Intermediate course
Project Intro Intermediate course
Project Intro Intermediate course
Project Intro Intermediate course
Project Intro Intermediate course
Dreamweaver 8 Introduction course
Project Intro Intermediate course
Project Intro Intermediate course
Milestones
how do i create a link
For upcoming training course dates see: Pricing & availability
RE: milestones
Hi There are at least five ways of doing this. Three of the most common ways however are:
left click (and drag) from one bar in the Gantt chart to another
block select two or more tasks and click on the link tasks button on the toolbar
double click a task and from the predecessors tab choose a task
Hope this helps - do let us know if you have any further questions.