Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training in london - Standardise calendars and working time

ms project training in london - Standardise calendars and working time

resolvedResolved · Low Priority · Version Standard

replyReply Wed 30 May 2007, 14:17Delegate Ibrahim said...

Ibrahim has attended:
Excel Advanced course
Excel VBA Intro Intermediate course

Standardise calendars and working time

Is there a quick way to standardise calendars and working times across multiple project plans without changing their schedule?

For example, when several Project documents covering a several-month period need to be integrated into one plan and their original authors have used templates with slightly different assumptions?

For upcoming training course dates see: Pricing & availability

replyReply Thu 7 Jun 2007, 16:25Trainer David said...

RE: Standardise calendars and working time

Ibrahim

Are you using project server?

regards

dave

replyReply Thu 7 Jun 2007, 16:28Delegate Ibrahim said...

RE: Standardise calendars and working time

Hi Dave,

No, we aren't using Project Server.

Regards,

Ibrahim

replyReply Tue 24 Jul 2007, 08:57Trainer David said...

RE: Standardise calendars and working time

Ibrahim,

sorry for very late reply, but i cant find an answer to this, have you?

david

replyReply Tue 24 Jul 2007, 09:44Delegate Ibrahim said...

RE: Standardise calendars and working time

No, I'm afraid not

replyReply Mon 6 Aug 2007, 16:44Trainer David said...

RE: Standardise calendars and working time

neither have I

 

Ms project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.

View all MS Project hints and tips