ms project training - Link

resolvedResolved · Low Priority · Version Standard

replyReply Thu 31 May 2007, 14:08Delegate Jatinder said...

Jatinder has attended:
Project Intro Intermediate course

Link

How do i create a start to start link?

For upcoming training course dates see: Pricing & availability

replyReply Thu 7 Jun 2007, 14:55Trainer Tracy said...

RE: Link

Hi Jatinder,

Thanks for the question

On the View menu, click Calendar.
Hold down CTRL, and click each task you want to link.
Click Link Tasks .

Once you have created the link you can then double click on it and change it to Start to Start using the drop down box.

Hope that helps

Tracy

 

Ms project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard