microsoft.project.course - milestone
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft.project.course - Milestone

microsoft.project.course - Milestone

resolvedResolved · Low Priority · Version Standard

replyReply Wed 6 Jun 2007, 15:24Delegate Karen said...

Karen has attended:
Project Introduction course

Milestone

How do I create a milestone??

For upcoming training course dates see: Pricing & availability

replyReply Thu 7 Jun 2007, 10:26Trainer Tracy said...

RE: milestone

Hi Karen,

Thanks for the question

To set a milestone you must enter it as a task of zero duration

Tracy

 

Ms project tip:

Autofit column width – Project (all versions)

a. Highlight the column or columns you wish to alter the width of.
b. Double click the dividing line between the columns. This dividing line is the break between the columns on the column headers (grey buttons showing the column letter at the top of each column). When you hover your mouse over one of these dividing lines the point will change and show an arrow pulling a line in two directions. When you have this mouse pointer you should double click to get Project to automatically set the column width to fit the contents of the column (autofit)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard