microsoft+project+training - Linking several tasks

resolvedResolved · Low Priority · Version Standard

replyReply Wed 6 Jun 2007, 16:33Delegate Cesar said...

Cesar has attended:
Project Introduction course

Linking several tasks

How to link several small tasks into a large task

For upcoming training course dates see: Pricing & availability

replyReply Wed 6 Jun 2007, 17:16Trainer Andrew said...

RE: linking several tasks

Hi Cesar

One way to combine several tasks is to create a summary task.

Above the list of tasks that you'd like to group together insert a new blank line and enter the name of the group or summary. Then select the tasks you'd like to include in this group and click on the indent button on the toolbar. The tasks will be indented slightly to the left and the summary task will be boldened.

Hope this helps - do let us know if you have any other questions.

Kind regards

Andrew

 

Ms project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard