how do i create a milestone of more than 0 days?
For upcoming training course dates see: Pricing & availability
RE: milestone
Hi Sarah
Thank you for your question.
To mark a task as a milestone with a duration of more than 0 days, click Task Information , and then click the Advanced tab. In the Duration box, enter the task duration, and then select the Mark task as milestone check box.
I hope this helps.
Amanda
|