microsoft project training - Split tasks

resolvedResolved · Low Priority · Version Standard

replyReply Fri 8 Jun 2007, 16:39Delegate Martyn said...

Martyn has attended:
Project Intermediate course

Split tasks

how do you split tasks.

For upcoming training course dates see: Pricing & availability

replyReply Mon 11 Jun 2007, 16:58Trainer Amanda said...

RE: split tasks

Hi Martyn

Thank you for your question.

To split a task:

1. In the Gantt chart, right-click on the box representing the task you wish to split.
2. Select Split task from the menu.
3. Hold your mouse over the box representing the task, at the point you wish to split it. Then drag to create the split.

Amanda

 

Ms project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)