microsoft project training - Split tasks
Resolved · Low Priority · Version Standard
For upcoming training course dates see: Pricing & availability
RE: split tasks
Hi Martyn
Thank you for your question.
To split a task:
1. In the Gantt chart, right-click on the box representing the task you wish to split.
2. Select Split task from the menu.
3. Hold your mouse over the box representing the task, at the point you wish to split it. Then drag to create the split.
Amanda
|