microsoft project courses - Presentation

resolvedResolved · Low Priority · Version Standard

replyReply Fri 8 Jun 2007, 16:40Delegate Brian said...

Brian has attended:
Project Intermediate course

Presentation

how do you insert a photo to the gantt chart pointing to the activity?

For upcoming training course dates see: Pricing & availability

replyReply Mon 11 Jun 2007, 15:24Trainer David said...

RE: presentation

Brian

Could you expalin what you want to do a little more clearer.

regards

dave

 

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.