microsoft project course - Milestone

resolvedResolved · Low Priority · Version Standard

replyReply Tue 12 Jun 2007, 14:04Delegate Owusu said...

Owusu has attended:
Project Intro Intermediate course

Milestone

milestone

For upcoming training course dates see: Pricing & availability

replyReply Tue 12 Jun 2007, 15:42Trainer David said...

RE: milestone

Owusu

Set the duration for 0 (zero days)

regards

david

 

Ms project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard