microsoft project 2003 training - Link

resolvedResolved · Low Priority · Version Standard

replyReply Tue 12 Jun 2007, 14:04Delegate Tim said...

Tim has attended:
Project Intro Intermediate course

Link

What is a link?

For upcoming training course dates see: Pricing & availability

replyReply Tue 12 Jun 2007, 15:45Trainer David said...

RE: Link

Tim

A link between tasks determines how the tasks are related, the default link is finish to start, ie when the predecessor ie A finishes, the successorie B can start.


regards

david

 

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips