ms project course - Baseline

resolvedResolved · Low Priority · Version Standard

replyReply Wed 20 Jun 2007, 17:41Delegate Rob said...

Rob has attended:
Project Intermediate course

Baseline

How do you save a baseline

For upcoming training course dates see: Pricing & availability

replyReply Thu 28 Jun 2007, 17:26Trainer Andrew said...

RE: baseline

Hi Rob

To save your baseline go to to Tools menu, then Tracking then choose Save Baseline.

Click on OK to set the baseline for your project.

Hope this helps,

Do let us know if you have further questions.

Kind regards,

Andrew

 

Ms project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard