Can I delete a restraint straight from the task bar?
For upcoming training course dates see: Pricing & availability
RE: RESTRAINTS
Hi Joe
It looks like you may be enquiring about Constraints that have been added to a task. All tasks have a constraint the default being "As soon as possible". If your task has some other kind of constraint set then switching back to this default setting will have the effect of releasing the task from date constraints. To do this double click on the task and go to the advanced tab. From here set the constraint type to "As soon as possible". Don't worry about clearing the date box to the right - when you click on OK Project will remove any constraint date set.
I hope this is helpful - do let us know if you require further information.