microsoft project courses - Calendars

resolvedResolved · Low Priority · Version Standard

replyReply Fri 6 Jul 2007, 14:19Delegate Sharon said...

Sharon has attended:
Project Intro Intermediate course

Calendars

how do i set a calendar

For upcoming training course dates see: Pricing & availability

replyReply Fri 13 Jul 2007, 12:58Trainer Andrew said...

RE: calendars

Hi Sharon

Thanks for your question - from the Tools menu in Gantt chart view click on change working time... From this dialogue box you can set working and non working days for your calendars as well as create new calendars.

To choose a calendar to apply to your entire project go to the Project menu then Project information and choose the calendar on which you would like to base your project.

I hope this answers your question - do let us know if you need any further information.

Kind regards,

Andrew

 

Ms project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard