microsoft project training - Calendars

resolvedResolved · Low Priority · Version Standard

replyReply Tue 10 Jul 2007, 16:19Delegate Paul said...

Paul has attended:
Project Intermediate course

Calendars

Can you change a project calendar (ie standard working hours from 8 to 7) after a project has started and has been baselined?

For upcoming training course dates see: Pricing & availability

replyReply Fri 13 Jul 2007, 13:22Trainer Andrew said...

RE: Calendars

Hi Paul

You can make the changes you describe. You may also wish to change the default value for the duration of a day to match the changes in your calendar. To do this go to Tools Options Calendar and set your Hours per day and default start time to align with the changes you make to your calendar.

I hope this is helpful - do let us know if we can be of further assistance.

Kind regards,

Andrew

 

Ms project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.