Calender set Up
Darren has attended:
Please advise on 24hr working when 2 teams are working equal shifts of 12 hrs each
RE: Calender set Up
Hi Darren. You base calender should be set to 24hr when you start the plan in Project. When you come to specifying either teams or individuals, you should then create bespoke calenders for them for their 12 hr shifts.
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||