microsoft project training - Links

resolvedResolved · Low Priority · Version Standard

replyReply Tue 24 Jul 2007, 14:00Delegate Neil said...

Neil has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Links

How do I create a link - question posed by tutor to activate membership!

For upcoming training course dates see: Pricing & availability

replyReply Wed 25 Jul 2007, 06:36Trainer Tracy said...

RE: Links

In answer to you question:-

In the Task Name field, select the tasks you want to link.
Click link Tasks button on the toolbar

Enjoy your membership

Tracy

 

Ms project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.