microsoft+project+training - Baseline

resolvedResolved · Low Priority · Version Standard

replyReply Thu 26 Jul 2007, 14:03Delegate Rumit said...

Rumit has attended:
Project Introduction course
Project Intermediate course

Baseline

How do I save a baseline?

For upcoming training course dates see: Pricing & availability

replyReply Sun 29 Jul 2007, 05:55Trainer Tracy said...

RE: Baseline

Hi Rumit,

On the Tools menu, point to Tracking, and then click Save Baseline.

Hope that helps
Tracy

 

Ms project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes