microsoft project training - Milestones
Resolved · Low Priority · Version Standard
Ava has attended:
Project Intro Intermediate course
Milestones
Is it possible to set a duration on the number of days it is estimated for a task to be completed on a task list (duration) without the Milestone turning into a bar
For upcoming training course dates see: Pricing & availability
RE: Milestones
Hi Ava
Yes you can. Create your task with the required duration then double click it to go to task information and on the advanced tab check the box to show as milestone. Project redraws your task as a milestone followed by an exended dependency arrow to reflect the duration you entered.
Hope this helps - let us know if you have any further questions.
kind regards,
Andrew
|