microsoft-project-training - Baselines

resolvedResolved · Low Priority · Version Standard

replyReply Fri 17 Aug 2007, 14:01Delegate Stephen said...

Stephen has attended:
Project Intro Intermediate course
Excel VBA Intro Intermediate course

Baselines

Are you able to save multiple baslines for a project?

For upcoming training course dates see: Pricing & availability

replyReply Fri 17 Aug 2007, 16:29Trainer Andrew said...

RE: Baselines

Hi Stephen

Thanks for your question - yes you can. From the Tools menu choose tracking then save baseline. From the dialogue box click on the dropdown to see a list of the available baselines you can save.

I hope this is helpful. All the best with MS Project.

Kind regards,

Andrew

 

Ms project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard