ms project training course - microsoft project views
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training course - Microsoft Project Views

ms project training course - Microsoft Project Views

resolvedResolved · Low Priority · Version Standard

replyReply Fri 17 Aug 2007, 14:01Delegate Caroline said...

Caroline has attended:
Project Intro Intermediate course

Microsoft Project Views

How do I hide some of the rows in my project sheet so that only some of the summary tasks show?

For upcoming training course dates see: Pricing & availability

replyReply Fri 17 Aug 2007, 16:34Trainer Andrew said...

RE: Microsoft Project Views

Hi Caroline

Using filters you can show only summary tasks that are relevant to your requirements. Click on the autofilter button (the funnel on the formatting toolbar) to turn on filters then apply your criteria using the drop down triangles beside each column name.

I hope this helps - do let us know if you have any further questions.

Kind regards,

Andrew

 

Ms project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.