microsoft professional project server training - what defines baseline
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft professional project server training - What defines the baseline?

microsoft professional project server training - What defines the baseline?

resolvedResolved · Low Priority · Version Standard

replyReply Tue 4 Sep 2007, 15:04Delegate Alex said...

Alex has attended:
Project Intro Intermediate course

What defines the baseline?

As above question

For upcoming training course dates see: Pricing & availability

replyReply Mon 10 Sep 2007, 16:40Trainer Andrew said...

RE: what defines the baseline?

Hi Alex

The baseline is a snapshot of your project created when you go to Tools > Tracking > Baselines and choose "save baseline"

Project stores your duration, start, finish, cost and work values for your tasks so that later on you can compare your baseline snapshot against your current position.

You can view this information by switching to the tracking gantt view.

I hope this is helpful - do let us know if you have any further questions.

Kind regards,

Andrew

 

Ms project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.