advanced ms project - mile stone
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » advanced ms project - Mile stone

advanced ms project - Mile stone

resolvedResolved · Low Priority · Version Standard

replyReply Fri 14 Sep 2007, 14:06Delegate Anthony said...

Anthony has attended:
Project Intro Intermediate course

Mile stone

how do i create a mile stone

For upcoming training course dates see: Pricing & availability

replyReply Mon 1 Oct 2007, 14:50Trainer Amanda said...

RE: mile stone

Hi Anthony

Thanks for your question.

To create a milestone:

1. On the View menu, click Gantt Chart.
2. Type 0 in the Duration field of the task you want to change.
3. Press ENTER.
When you enter a duration of zero for a task, Project displays the milestone symbol (a diamond shape) on the Gantt Chart on that day.

Amanda

 

Ms project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard