microsoft professional project server training - Calendars

resolvedResolved · Low Priority · Version Standard

replyReply Mon 24 Sep 2007, 15:13Delegate Daniel said...

Daniel has attended:
Project Intro Intermediate course

Calendars

How do I format the project so that the red line for today's date appears in the Gantt chart?

For upcoming training course dates see: Pricing & availability

replyReply Tue 25 Sep 2007, 11:40Trainer Anthony said...

RE: Calendars

Hi Daniel. Right click on the Gantt chart and select Progress Lines. Then make sure the "Always display current Progress line" is selected with the "At current date" option ticked. This should include the red line on your Gantt chart.

Hope this helps,

Anthony

 

Ms project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips