Calendars
How do I format the project so that the red line for today's date appears in the Gantt chart?
For upcoming training course dates see: Pricing & availability
RE: Calendars
Hi Daniel. Right click on the Gantt chart and select Progress Lines. Then make sure the "Always display current Progress line" is selected with the "At current date" option ticked. This should include the red line on your Gantt chart.
Hope this helps,