microsoft project consulting - Projects (resource work times)

resolvedResolved · Low Priority · Version Standard

replyReply Mon 8 Oct 2007, 14:55Delegate Carl said...

Carl has attended:
Project Introduction course
Project Intermediate course
Project Server Admin course

Projects (resource work times)

My project is to feature varying types of labour including sub contract, manufacturing and office based work: How can I alter and manage the numerous different calendars?

For upcoming training course dates see: Pricing & availability

replyReply Thu 18 Oct 2007, 13:09Trainer David said...

RE: Projects (resource work times)

we cover this on our Advanced course, if you bring the project to the course the trainer will be able to go through this with you

 

Ms project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts