ms project training courses - Lag time

resolvedResolved · Low Priority · Version Standard

replyReply Tue 9 Oct 2007, 15:45Delegate Nutan said...

Nutan has attended:
Project Intro Intermediate course

Lag time

How do you put in lag time?

For upcoming training course dates see: Pricing & availability

replyReply Thu 18 Oct 2007, 13:27Trainer David said...

RE: Lag time

task information - predecessors - add days for lag times use negative number for negative lag or overlapping tasks..

 

Ms project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard