Is it possible to label a chain link. For example Task 1 is 'Create Building Plan' and Task 2 is 'Implement Building Plan.' The lag time would be the period in between awaiting responses. Could 'Awaiting responses from X,Y,Z' be placed next to the line linking Tasks A and B?