project/server/2003/training - Resources

resolvedResolved · Low Priority · Version Standard

replyReply Mon 19 Nov 2007, 16:02Delegate Steve said...

Steve has attended:
Project Intro Intermediate course

Resources

How do I allocate resources from a common pool and
how do I roll-up the resources allocated to several projects?

For upcoming training course dates see: Pricing & availability

replyReply Wed 21 Nov 2007, 10:50Trainer Stephen said...

RE: Resources

Hi Steve,

Simply create a blank project and then populate the resource sheet with the resources in your common pool. Save this, calling it something like "resource pool" etc.

Then with the resource pool open, open the projects that are to use the resource pool and click on tools-resource sharing-share resources.

Then choose the option that allows the project to get its resources from the resource pool and save the changes.

Then if you reopen the resource pool it will give you the opportunity to open a master project that shows all the rpojects using the resource pool.

Regards

Stephen

 

Ms project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard