project server consultants - resource allocation
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » project server consultants - Resource Allocation

project server consultants - Resource Allocation

resolvedResolved · Low Priority · Version Standard

replyReply Mon 19 Nov 2007, 16:03Delegate Sarah said...

Sarah has attended:
Project Intro Intermediate course

Resource Allocation

I will work 100% on the project until a certain milestone and then will work only 50%. How can I make that automatic in Project?

For upcoming training course dates see: Pricing & availability

replyReply Wed 21 Nov 2007, 16:40Trainer Stephen said...

RE: Resource Allocation

Hello Sarah,

Thanks for your question.

This is possible but you would need to write a fair amount of VBA code and it would be pretty difficult. The effort is probably not worth the result and your best bet would be simply change your availability at the scheduled time for the milestone, and then attach a note reminding you to cahnge it if the milestone date changed.

Regards

Stephen

 

Ms project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard