Forum home » Delegate support and help forum » Microsoft Project Training and help » project server consultants - Microsoft Project

project server consultants - Microsoft Project

resolvedResolved · Low Priority · Version Standard

replyReply Thu 22 Nov 2007, 14:03Delegate Hannah said...

Hannah has attended:
Project Intro Intermediate course
Project Advanced course

Microsoft Project

How do i customize my reports using Office 2003?

For upcoming training course dates see: Pricing & availability

replyReply Thu 22 Nov 2007, 16:52Trainer Stephen said...

RE: Microsoft Project

Hi Hannah,

Thanks for the question.

If you click on View-Reports-Custom and then select new the system will ask you a series of questions that allow you to choose the base table, group, filter and sort the information. You can also format the text etc.

The key to success here is to create your own table that contains exactly the information that you require in your report. To do this click on View-Tables-Custom and click new. You are then asked to name your table and select the required fields.

Regards

Stephen

 

Ms project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)