+project server +training - Dependency Linking

resolvedResolved · Low Priority · Version Standard

replyReply Wed 19 Dec 2007, 13:54Delegate Ava said...

Ava has attended:
Project Intro Intermediate course

Dependency Linking

Is it possiblke to link between seperate project plans

Ii.e a dependency reminder that is linked to a task on another project

For upcoming training course dates see: Pricing & availability

replyReply Thu 20 Dec 2007, 11:27Trainer Stephen said...

RE: Dependency Linking

Hi Ava

Thankyou for you question

If you projects are using a common resource pool then if you open the resource pool, choosing the option to also open a master file; then you can link tasks across projects in the same way as within an individual project.

If the projects do not use a common resource pool, then you can open a blank project file and insert the individual projects into it using Insert-Project.

Once again at that point you can link tasks across individual projects as if they were in the same project

Regards

Stephen

 

Ms project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard