+project server +training - Dependency Linking
Resolved · Low Priority · Version Standard
Ava has attended:
Project Intro Intermediate course
Dependency Linking
Is it possiblke to link between seperate project plans
Ii.e a dependency reminder that is linked to a task on another project
For upcoming training course dates see: Pricing & availability
RE: Dependency Linking
Hi Ava
Thankyou for you question
If you projects are using a common resource pool then if you open the resource pool, choosing the option to also open a master file; then you can link tasks across projects in the same way as within an individual project.
If the projects do not use a common resource pool, then you can open a blank project file and insert the individual projects into it using Insert-Project.
Once again at that point you can link tasks across individual projects as if they were in the same project
Regards
Stephen
|