ms-project-training - Microsoft Project

resolvedResolved · Low Priority · Version Standard

replyReply Mon 14 Jan 2008, 17:40Delegate Eamon said...

Eamon has attended:
Project Intermediate course

Microsoft Project

How to create task links

For upcoming training course dates see: Pricing & availability

replyReply Wed 16 Jan 2008, 20:45Trainer Andrew said...

RE: Microsoft Project

Hi Eamon

Thanks for your question.

Try one of these:

in the predecessor column for your successor task type the ID or Row number of the predecessor followed by the relationship you wish to make (eg 4FS)

Hover over the bar of the predecessor and when you can see the four headed arrow left click and drag to the bar of your successor. Let go to link (FS) Double click the link to switch to a different kind of relationship.

Hope this helps - let us know if you have any further questions.

Kind regards,

Andrew

 

Ms project tip:

Enter a Date

You can enter today's date (or tomorrow's date) in a date field, by simply typing in the word 'today'or 'tomorrow' and Project will insert the date for you.