consulting ms project - MSP Calendars

resolvedResolved · Low Priority · Version Standard

replyReply Wed 23 Jan 2008, 08:17Delegate Stephen said...

MSP Calendars

How do I rename (or delete) a task calendar (not a Project base calendar but new or copied calendar)?

Thank you!

For upcoming training course dates see: Pricing & availability

replyReply Tue 5 Feb 2008, 16:42 Edited on Tue 5 Feb 2008, 16:42Trainer Stephen said...

RE: MSP Calendars

Hi Stephen

Thanks for your question

If you click on Tools-organiser and select the calendars tab you will be presented with a list of the calendars in both the global template and in the file you have open. You can then select the calendar in question and delete or rename it as required.

Regards

Stephen

 

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips